Imagine my horror as I watched my client’s Cobra production system open, with the Project list table completely bereft of the project we’d been working on for the last 7 months
How Cobra Calculates EV on % Complete Work Packages
For the most part, Earned Value Techniques (EVTs) on work packages are self explanatory; 50-50, 0-100, Milestone and so on. But a couple of them don’t behave as one might expect
Bulk loading rates from CSV files in Cobra 5.0
There’s been some rumors kicking around that bulk loading of rates in Cobra 5.0 had some issues. Today I loaded a huge and complex rate CSV file that boasts over 10,000 rows. It took several days to develop the
Migrating Projects from Deltek Cobra 4.7 to 5.0
With increasing frequency, clients have been interested in learning how to migrate EVMS data from Deltek Cobra 4.7 to 5.0 with the lowest amount of risk. There are several things to consider before undertaking the migration. First, the best approach may depend on your current situation. If you have an in-progress program that has just […]