Why Schedule Risk Analysis is a Good Idea

Our friends at Barbecana submitted this interesting article explaining why Schedule Risk Analysis is a good idea.

The Value

As part of the project management process, a project schedule will be defined, typically using the Critical Path Method (CPM) technique, that identifies the activities (tasks) that need to be performed to fulfill the project objectives, how long each activity is expected to take, the order in which the activities must be performed, and often the resources required to perform the work.

The trouble with the CPM technique is that it does not take into account uncertainty and because of this it tends to be inherently optimistic in the forecast it provides for project completion.

By understanding the effect of uncertainty, both in terms of estimate uncertainty (lack of knowledge) and event uncertainty (random external threats and opportunities), we can focus our estimating and management effort on activities that are likely to have the largest effect on the project outcome. This reduces management effort and cost and allows us to make commitments that are more realistic and achievable.

CPM is Inherently Optimistic

There is always uncertainty associated with activity execution. There may be less uncertainty associated with work that has been performed before and is well understood, but it is still there. Machines fail, staff have good days/bad days, and weather happens. Consider the following example where we can assume our estimates are good, uncertainty is equally likely to have a beneficial vs detrimental impact, and historically our average actual execution time is in line with estimates.

Schedule Risk Analysis Fig 1

If each activity takes 5 days to execute, the project should complete at the end of day 10. However, what happens if Activity A takes 6 days to complete? As good project managers we will observe the overrun and we can focus our efforts to bring Activity B in early. If we are successful the project may still complete on day 10.

Now consider those same two activities executed in parallel:

Schedule Risk Analysis Fig 2If again, each activity takes 5 days to execute, the project should complete at the end of day 5. However, what happens if activity A takes 6 days to execute? The project completion will slip to day 6 and there’s nothing we can do to Activity B to improve the situation. In fact, if B has any effect at all, it will only be to delay the project further.

Let’s tabulate the possible outcomes of activity A and B in our parallel example:


Activity A


Activity B


Project Completion

   On-Time/Early    On-Time/Early    On-Time/Early
   Late    On-Time/Early    Late
   On-Time/Early    Late    Late
   Late    Late    Late

From the table we can see that, even assuming symmetrical uncertainty on the two individual activities, we only have a one in four (25%) chance of the project finishing on-time or early.

This phenomena is called Merge Bias and is why projects scheduled using CPM are inherently optimistic and produce forecast project completion dates that are often unrealistic and unachievable.

Merge Bias, in our modern complex projects with multiple parallel paths, will affect the project outcome even if estimates and execution are historically excellent.

Schedule Risk Analysis (SRA) using Monte Carlo Simulation

CPM uses a single estimate for activity duration. A better model would use a range of estimates that reflect the possible variation in execution for each activity. These are called Three Point Estimates. There is often concern that obtaining a range of estimates for every activity will be arduous and time consuming. This doesn’t have to be the case. In fact, an initial analysis of the project using generic estimates for all activities (e.g. ±25%) can usually identify good candidates for more detailed analysis using historical data, expert opinion, or perhaps confidence (or lack thereof) in the original estimate expressed during risk workshops.

Schedule Risk Analysis will then simulate the execution of the project many times, using durations sampled from the range specified for each activity, and produce a range of dates over which the project may finish.

Schedule Risk Analysis Fig 3

The histogram bars shows the chance of the project (or activity/milestone) finishing on a specific date.

The cumulative S-Curve shows the probability of finishing by a specific date.

The chart shows we only have a 6% chance of achieving the January 23 finish date suggested by CPM.

Based on this chart we might commit to deliver on March 17 because this gives us a higher (80%) chance of success.

Sensitivity analysis can identify the top contributors to uncertainty in the project/deliverable outcome.

Schedule Risk Analysis Fig 4

Activities listed on the sensitivity (a.k.a. Tornado chart) report are good candidates for more in-depth estimating and also consideration for logic/duration changes in order to compress the schedule. By focusing management effort on activities listed on the report, management time/cost can be reduced and the chance of project success increased.

Summary

Schedule Risk Analysis can be an easy way to ensure commitments are realistic and improve your chance of success while reducing project costs. Embracing risk can improve confidence and ultimately profitability.