Updating Activities in Primavera P6

A common request that we receive is from folks wanting to understand how to update work progress using the update features in Primavera P6 Professional. This article describes the major steps to updating your schedule based upon the progress of your activities. It does not go into detail about the different Percent Complete Types. This article assumes your Percent Complete Type is Duration.

It is recommended that you read the related blog entitled “Scheduling Baselines in Primavera P6”

The Three Step Process

Updating the schedule with actual progress is a three step process that may be repeated at any desired interval, such as once per week. In Figure 1 we have sketch of a schedule.

Updating Activities in Primavera P6 Fig 1Figure 1

This diagram displays a schedule with non-critical, critical, and actual work bars. Additionally, it shows the Data Date, which is the current date of the project. If you want to provide weekly project updates then you would:

  1. Enter project status up to the end of the respective week
  2. Move the data date forward one week
  3. Reschedule the project

Figure 2 displays the step 1 status updates for week two.

Updating Activities in Primavera P6 Fig 2Figure 2

In Figure 3, step 2, the Data Date is moved forward one week.

Updating Activities in Primavera P6 Fig 3Figure 3

Finally, Figure 4, step 3, displays the activity progress after scheduling the project.

Updating Activities in Primavera P6 Fig 4Figure 4

The process, again, is Enter Status, Move Data Date, and Recalculate the Schedule. Get the rhythm down for this three step update process and you will avert many of the problems associated with project status updating. One note of advice: always make a backup copy of your schedule before commencing the update process.

Construction Project Example

Figure 5 displays an example schedule describing the structural phase of a building construction project.

Updating Activities in Primavera P6 Fig 5aFigure 5

Note, in particular, the Percent Complete Type of all activities is Duration; the simplest % complete type to implement. The yellow bars displayed in the Gantt chart, Figure 5, represent the baseline.

Week One Status Update

To prepare for the enter status step of the update process select activity A and then select the Status tab from the activity bottom details. Commence the status update by clicking the Started toggle and entering a Duration % complete of 80%, Figure 6.

Updating Activities in Primavera P6 Fig 6Figure 6

The remaining duration of 1-day is automatically computed for the 5-day activity. Now change the Current Data Date. Select the Schedule icon in the tools group at the top of the screen or select Tools | Schedule from the main drop down menu. Either method will activate the Schedule dialog, Figure 7.

Updating Activities in Primavera P6 Fig 7aFigure 7

Select the Current Data Date ellipse, again, Figure 7. In the calendar, Figure 8, advance the Data Date by one week.

Updating Activities in Primavera P6 Fig 8aFigure 8

Finally, recalculate the schedule and your Gantt chart will look similar to that shown in Figure 9.

Updating Activities in Primavera P6 Fig 9aFigure 9

Week Two Status Update

The second weeks’ update requires you to enter the status of two activities that are progressing during this week. First, select Task A and in the Status tab check the finished toggle, Figure 10.

Updating Activities in Primavera P6 Fig 10Figure 10

Second, select activity B and in the Status tab check the started toggle and set the Duration % complete to 40%, Figure 11.

Updating Activities in Primavera P6 Fig 11Figure 11

Primavera P6 computes the remaining duration of 6-days. Now select Tools | Schedule > Current Data Date ellipse, and advance the Data Date one week to January 19th, Figure 12.

Updating Activities in Primavera P6 Fig 12aFigure 12

Recalculate the schedule for week two updates and view your updated Gantt chart, Figure 13.

Updating Activities in Primavera P6 Fig 13aFigure 13

Week Three Status Update

To get you into the rhythm of making status updates we update our sample project for week three. Enter status by selecting task B and in the Status tab setting the Duration % complete to 90%, Figure 14.

Updating Activities in Primavera P6 Fig 14Figure 14

Move the Data Date one week forward to January 26th, Figure 15.

Updating Activities in Primavera P6 Fig 15aFigure 15

Recalculate the schedule to arrive at your three week updated schedule, Figure 16.

Updating Activities in Primavera P6 Fig 16aFigure 16

Summary

Primavera P6 has three different ways to define activity percent complete; the simplest of these three is Duration % complete. Though the % complete type may add complexity to the update process, overall status updating is a straight forward three step process:

  1. Enter status
  2. Move Data Date
  3. Recalculate the schedule

Maintain the accuracy of your schedule updates by repeatedly implementing this three-step process. Once you have this three step process down, then you can explore the complexities of the Percent Complete Types to further enhance the accuracy of your schedule updates.