• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Site-Logo
Phone 703-910-2600

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Snapshots in Acumen Fuse Explained

You are here: Home / Deltek Acumen / Snapshots in Acumen Fuse Explained

June 29, 2023 By Ten Six

Snapshots in Acumen FuseMovieSnapshots in Acumen Fuse are simply a project that has been added to the workbook and represents a project in some state of progress. For example, let’s say you have a project baseline loaded into an Acumen workbook. After a month, you have an updated version of that project, and you want to compare it to the original baseline. To do this you would enter it as a snapshot of the original project.

We’ve produced a short video explaining snapshots in Acumen Fuse.

If you don’t want to watch the video, here’s a step-by-step guide as to how you use Snapshots in Acumen Fuse.

First, we’re going to start with a new workbook.

Them, in the Get External Data From tool group, click on the Oracle Primavera button and select “Single Project from a P6 XER file” as shown below in Figure 1.

Get External Data From tool groupFigure 1

We’ll be using the Ten Six training project data for this example, so we’re going to find the ‘Titan II Orbiter Baseline IMS.xer’ file. Then click Open, shown in Figure 2.

Snapshots in Acumen FuseFigure 2

This will link the Titan II Orbiter IMS project baseline in the Acumen Workbook list (Figure 3).

Acumen Workbook listFigure 3

Now we’re going to left click on the Titan II Orbiter IMP workbook link (Figure 4).

IMP workbook linkFigure 4

It must be selected. Then, click the Oracle Primavera button once more and choose Multiple Projects from a P6 XER file, shown below in Figure 5.

Oracle Primavera button in AcumenFigure 5

In the Open dialog, we navigate to our Acumen Fuse Training Data folder and use the Shift key to select all the Titan II Orbiter XER files, dated 2018-10-31 thru 2019-02-28.

Then we click Open, Figure 6.

Import All ProjectsFigure 6

This will load each of the monthly status updated XER files into the Workbook below the original baseline file. These are snapshots from the project at monthly intervals. And if you did that correctly you should see all the snapshots are indented from the baseline IMS.

Now click on the Import All Projects button in the Import tool group, Figure 7.

Import All ProjectsFigure 7

You are now ready for some trend analysis as seen below in Figure 8.

Snapshots in Acumen FuseFigure 8

I hope this gives you some idea how to use Snapshots in Acumen Fuse. You can also see other Deltek videos by Ten Six here as well as subscribe to our YouTube channel to receive notifications of when we post a new video.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2023 Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us