Primavera P6 Professional and Schedule Automatically Quick Tip

Is it possible in Primavera P6 Professional to schedule automatically?

I recently provided a client an updated schedule and the goods news they would meet the contract completion deadline by one week. The only problem was I neglected to recalculate the schedule. When this mishap was discovered I subsequently recalculated the schedule and found out that the schedule would miss the contract completion deadline by 3 days. Could this missed oversight have been avoided?

This article shows to get Primavera P6 Professional to schedule automatically.

Schedule Automatically in Primavera P6 Professional

The default setting in Primavera P6 Professional schedule options is non-automatic manual scheduling. Figure 1 displays the schedule options dialog, and the toggle to “schedule automatically when a change affects dates”.

Primavera P6 Professional and Schedule Automatically 1Figure 1

When we toggle on automatic scheduling, Primavera P6 will schedule automatically. It will update the schedule when a change affects dates.

The outstanding question is if you are planning a project schedule which setting is more appropriate: automatic or manual scheduling? Your selection depends in part on your confidence in Primavera P6 Professional’s ability to undo changes made previous to a schedule calculation. Primavera P6 Professional does have an undo feature though. So, theoretically you should be able to reset changes made prior to a schedule calculation.

Summary

Setting Primavera P6 Professional to schedule automatically makes sense. This helps avoid the painful mistake of submitting reports on a schedule that has not been recalculated or rescheduled after changes affecting dates. The default setting in Primavera P6 Professional is manual scheduling, which can easily be toggled to automatic.

So the choice is yours in Primavera P6: manual or automatic scheduling? We recommend you set the scheduling to automatic while in the planning stage of your project. Also note any issues that may occur while using the automatic scheduling option.