• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Site-Logo
Phone 703-910-2600

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Video – Deltek Acumen Fuse Maturity Framework Explained

You are here: Home / Deltek Acumen / Video – Deltek Acumen Fuse Maturity Framework Explained

May 15, 2023 By Ten Six

Acumen Fuse Maturity FrameworkMovieThe Acumen Fuse Maturity Framework has five levels, S1-S5, that is used to identify schedule maturity. The stages flow so that each level leads to an increasing, higher quality and achievable project plan.

By following the Acumen Fuse Maturity Framework, projects can establish validated schedules that have accounted for risk, have been mitigated and optimized to achieve a target and satisfy the stakeholders and project team.

Let’s take a closer look at the five-stages of Acumen Fuse’s Maturity Framework:

S1 The Base: The original critical path method schedule which is unknown in quality and realism is imported into an Acumen workbook. In S1 the unvalidated schedule is reviewed and changes can be made to details or scenario copies of the schedule.

S2 Critiqued: The schedule is reviewed using Acumen Fuse Metrics. Areas that need improvement are identified. Schedule changes are made in the original schedule software or directly in Acumen S1.

S3 Risk-Adjusted: Uncertainty of duration and cost estimates are considered. Risk events both opportunities and threats are identified. Risks are listed in a risk register and mitigation of risk events is considered.

S4 Optimized: Optimization scripts are written and opportunities are investigated using Acumen Fuse 360 tools. The outcome from this stage is a fully optimized schedule whose final layout has full support from the project technical expert.

S5 Team Aligned: At this final stage, you can present your health-certified, risk-adjusted and optimized schedule to team members and stakeholders, knowing they will have increased confidence in achieving the schedule duration and cost target.

Reports and Spreadsheets can be produced at all stages of the Acumen Fuse Maturity Framework from S1-S5.

We’ve produced a short video explaining Deltek’s Acumen Fuse Maturity Framework for folks who prefer to see it in a visual format.

You can also see other Deltek videos by Ten Six here as well as subscribe to our YouTube channel to receive notifications of when we post a new video.

We have also produced a complete, self paced, video training class for Deltek Acumen Fuse. This class is available 24/7 and you can take it as many times as you like over a two year period!

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2023 Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us