Sizing the Gantt Chart for Printout in P6 Professional

Sizing the Gantt Chart for Printout in P6 Professional

Here we take a look at sizing the Gantt chart for printout on to a 11×17 sheet of paper to fit alongside your activity table.

You will most likely want your schedule printed to 11×17, the largest size a standard printer can accommodate. However, even though it is larger than 8.5×11, you still have limited paper room for your schedule. Hence, the Gantt chart needs to be as narrow as possible. It is a little bit of an art to have your Gantt chart shrink to a size suitable for fitting on your printout.

Here we demonstrate some tips and techniques sizing the Gantt chart for printout.

Our demonstration schedule is in Figure 1; we want to print the Gantt chart and activity table on an 11×17 sheet of paper.

P6 Demonstration Schedule

Figure 1

We choose File | Print Preview, Figure 2, to view a print preview.

Print Preview In P6

Figure 2

The print preview is displayed in Figure 3.

Sizing the Gantt Chart for Printout in P6 Professional

Figure 3

Observe the narrow Activity ID column: The shrink vertical grouping bands are on. This Group and Sort setting was written about in the blog Sizing the Activity Table for Printout in P6 Professional.

 The activity table looks good.

A closer look at the Gantt chart reveals start milestones that look chopped off at the beginning of the project and hidden task labels near completion, Figure 3. To correct this, we click the Page Setup icon in Figure 4.

Showing Milestones in P6

Figure 4

Our Timescale Start, Project Start (PS) and Timescale Finish, Project Finish (PF) were chosen from the ellipse (three periods square icon) dropdown menus, Figure 5.

Setting Timescale Start and Finish in P6

Figure 5

We want to modify these by making Timescale Start earlier than the PS (to fit in the milestone relationship lines) and Timescale Finish later than the PF (to fit in the task labeling on the right side of the Gantt chart). Figure 6 shows how we modify the Timescale Start PS by subtracting one day (1D) and Timescale Finish PF by adding one week (1W).

Modifying Timescale Start in P6

Figure 6

The print preview appears in Figure 7 and looks good.

Schedule Printout in P6

Figure 7

You usually want to add as many activity table columns as possible. Figure 8 demonstrates what happens to the Gantt chart when adding a Total Float, Activity % Complete, and Cost columns.

Showing Total Float, Activity % Complete, and Cost columns in P6

Figure 8

Our Gantt chart does not fit on the screen output. When we click File | Print Preview, less than half the schedule fits on the Gantt chart area, Figure 9.

Sizing the Gantt Chart for Printout in P6 Professional

Figure 9

To fit the schedule, we hover the mouse over the lower Timescale increment row, which is the day of the week for our “Week/Day 1” Timescale. So, we hover the mouse (highlighted by a blue circle) over the Timescale day of the week until the (Sherlock Holmes) magnifying glass appears. See Figure 10; the mouse now appears as a magnifying glass in this figure.

Adjusting the P6 Timescale

Figure 10

Then we left-click (a mouse left-click is represented by the smaller green circle highlighter) and drag the magnifying glass mouse to the left, Figure 11, which compresses the Timescale and, therefore, the Gantt chart.

Compressing the Timescale in P6

Figure 11

Figure 12 displays the Gantt chart after compressing the Timescale.

Compressing the Timescale In P6

Figure 12

Now we choose File | Print Preview, Figure 13.

File Print Preview Options in P6

Figure 13

Now, the Gantt chart print preview looks better, Figure 14.  

P6 Schedule

Figure 14

Figure 15 shows a close-up of the Gantt chart in the Print Preview with no label adjustments.

Sizing the Gantt Chart for Printout in P6 Professional

Figure 15

If you want to tweak the task labels displayed in Figure 15 further, you could modify the Timescale Finish PF and add two weeks (2W) to view the entire task labeling. We do not demonstrate tweaking the task label view. Again, refer to the article above for a primer on tweaking the PS and PF dates to fit relationship lines and task labeling on the Print Preview.

Another way to sizing the Gantt chart for printout, is to adjust the Timescale. In Figure 16, we right-click on the Gantt chart and choose Timescale from the popup menu.

Timescale Adjusting in P6

Figure 16

We then change the Date Interval from Week/Day 1 to Month/Week, Figure 17.

Date Interval Settings in P6

Figure 17

Great! But now we have too many vertical sight lines. To continue, we right-click the Gantt chart and choose Bar Chart Options from the popup menu, Figure 18.

P6 Bar Chart Options

Figure 18

We change the Vertical Lines – Minor from Day to Week, Figure 19.

Sizing the Gantt Chart for Printout in P6 Professional

Figure 19

We change the Vertical Lines – Major from Week to Month, Figure 20.

Adjusting Vertical Lines in P6

Figure 20

The print preview of the resulting schedule is in Figure 21.

Sizing the Gantt Chart for Printout in P6 Professional

Figure 21

We need to adjust it to fit the labeling at the end of the project tasks. To do this, we click page setup, Figure 22.

Labeling in P6

Figure 22

We add two weeks (2W) to the Timescale Finish PF, Figure 23.

Timescale adjustment in P6

Figure 23

The resulting schedule print preview is in Figure 24.

Schedule Printout in P6

Figure 24

A closeup of the scheduled Gantt chart print preview is in Figure 25, which looks good.

Close up of Schedule Printout in P6

Figure 25

Summary

Sizing the Gantt chart for printout in P6 needs a few adjustments to fit it and the activity table on one 11×17 sheet of paper.

  1. To better display relationship lines and labeling, subtract days from the project start PS and add weeks to the project finish PF. (You can also add months (M) or quarters (Q).
  2. To expand the activity table with additional data columns, we will likely need to compress the Gantt chart using the mouse magnifying glass, left-clicking, and dragging left.
  3. An alternative is to change the Timescale of the Gantt chart from Week/Day 1 to Month/Week to provide a higher-level view of the Gantt chart.
  4. Again, modify the Timescale start PS and Timescale finish PF accordingly to fit relationship lines and labeling on the Gantt chart.

You may also need to adjust the sight lines. For an additional demonstration of Gantt chart sight line adjustment, refer to the following:

Thus, we can manually adjust the Gantt chart timescale with the Sherlock Holmes mouse left-click and drag or automatically choose a different Date Interval for the Timescale and adjust the sight lines to match accordingly.