Sizing the Activity Table for Printout in P6 Professional

Sizing the Activity Table for Printout

Here’s some tips on sizing the activity table for printout to fit on an 11×17 sheet of paper.

You will most likely want your schedule printed to 11×17, the largest size a standard printer can accommodate. However, even though it is larger than 8.5×11, you still have limited paper real estate for your schedule. Hence, the activity table needs to be as narrow as possible. To narrow your task table, turn off the time stamp so your date columns come in narrower. Check this article out for primer on How To Display Time Stamps In Primavera P6.

But sometimes, this is insufficient to allow all the data columns in your task table to appear on your printout. This is when the “shrink vertical grouping bands” tool is handy.

This article demonstrates a quick tip for sizing the activity table for printout by shrinking vertical grouping bands to narrow your activity table.

In Figure 1, we have our schedule to demonstrate the sizing of the activity table accordingly.

Sizing the Activity Table for Printout

Figure 1

We begin by clicking File | Print Preview, Figure 2.

P6 Print Preview Option

Figure 2

Our schedule’s resulting Print Preview appears in Figure 3.

Sizing the Activity Table for Printout

Figure 3

The first thing we notice is the wrong paper size. We correct it by choosing the Print Setup icon in Figure 4.

P6 Print Setup

Figure 4

In the Print Setup dialog box, we do the following: (1) set the Printer Name to Adobe PDF (or equivalent), (2) select the 11×17 paper size, and (3) choose landscape orientation, Figure 5.

Select Printer

Figure 5

The schedule printout then looks like Figure 6.

Sizing the Activity Table for Printout

Figure 6

We cannot see the Gantt chart because we need to set the project start and finish of the Gantt chart. In Print Preview, we choose Page Setup, as shown in Figure 7.

P6 Print Preview

Figure 7

In Page Setup, we set the Timescale Start to Project Start (PS) and Timescale Finish to Project Finish (PF), as shown in Figure 8.

Set the P6 Timescale Start to Project Start

Figure 8

The resulting schedule printout appears in Figure 9.

P6 Schedule Printout

Figure 9

This looks better, but let’s subtract one day (1D) from the start and add (9D) to the conclusion so that start milestone relationship lines and task labels are not cut off at the beginning and end of the schedule. The adjusted Page Setup is displayed in Figure 10.

Primavera P6 Page Setup

Figure 10

The printout then becomes as follows in Figure 11.

Primavera P6 Printout

Figure 11

Now, our Gantt chart, Figure 11, looks way off. Adding nine days to the end of the project extended the Timescale so that the Gantt chart no longer fits on our printout.

Let us try to make it fit by making the activity table narrower. We can narrow the task table further by shrinking the vertical grouping bands. Figure 12 displays our demonstration schedule’s vertical grouping band total width, determined by the number of levels in the work breakdown structure (WBS), a hierarchical breakdown of all the project deliverables.

Sizing the Activity Table for Printout

Figure 12

A deliverable is the product or service you provide to your customer; it is the whole point and purpose of the project. The more WBS elements or deliverables in the schedule the wider the grouping bands total width.

We close the dialog and choose View | Group and Sort, Figure 13.

Primavera P6 View | Group and Sort Options

Figure 13

We toggle on “Shrink vertical grouping bands” Figure 14.

Sizing the Activity Table for Printout

Figure 14

Then we hoover our mouse (highlighted by a blue circle) on the vertical separator line between the Activity ID and Activity Name column headers, Figure 15.

Adjusting the Activity ID and Activity Name column headers in P6

Figure 15

We continue by left-clicking the mouse on this vertical separator line (the left-clicking of the mouse is indicated by a smaller green circle highlighter) and dragging to the left to narrow the Activity ID column, Figure 16.

Adjusting the Activity ID column in P6

Figure 16

The activity table and Gantt chart appear in Figure 17; the Activity ID column is noticeably narrower.

P6 activity table and Gantt chart

Figure 17

Figure 18 shows the Print Preview, where the activity table and Gantt chart fit on the printout.

Primavera P6 Print Preview

Figure 18

We now demonstrate what happens when we untoggled the shrink vertical grouping band setting. We click View | Group and Sort and, in Figure 19, choose to un-toggle this setting.

P6 View | Group and Sort

Figure 19

Notice in Figure 20 that we cannot see some characters in the Activity ID (codes) column. To fix this, we must left-click the header vertical separator line and drag it to the right.

Sizing the Activity Table for Printout

Figure 20

Summary

When sizing the activity table for printout,there are a few adjustments needed to the activity table to fit both the table and Gantt chart on one 11×17 sheet of paper:

  1. Choose your printer, set the paper size to 11×17, and set the orientation to landscape.
  2. In Page Setup Options, set the Gantt Timescale Start to PS and Timescale Finish to PF.
  3. Remove all columns in the activity table that do not include pertinent information.
  4. Make a narrower Activity ID column possible by turning on shrink vertical grouping bands.
  5. Left-click the Activity ID column header separator line and drag left to make narrower the activity table.
  6. Click File | Print Preview

You can also narrow the date columns by turning off the time stamp. For a primer on displaying the time stamp or not, refer again to this article How To Display Time Stamps In Primavera P6.

Among the Printer Setup, add/remove columns, date time stamp removal, and shrink vertical grouping bands, you have helpful tools to fit the tasks table and the Gantt chart on one 11×17 sheet of paper.