• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Site-Logo
Phone 703-910-2600

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Relationship Types in Primavera P6 Explained

You are here: Home / Primavera P6 / Relationship Types in Primavera P6 Explained

August 23, 2021 By TheP6Pro

Relationship Types in Primavera P6 ExplainedMovieA key part of robust schedules in Primavera P6 are built by using logical relationships across the network of activities. In this article, we will discuss the different relationship types in Primavera P6 available to schedulers, offering examples of their use. Better still, we have also produced a short video where users can visually see the varying differences between the relationship types used in Primavera P6.

In Primavera P6, a relationship refers to a link between two activities. This link describes the flow of work between tasks, as shown in Figure 1.

Relationship Types in Primavera P6Figure 1

For Example:

When a house is being built, work cannot start on the roof until the walls are complete.

Primavera P6 uses the terms predecessor and successor to describe the relationship between two activities, as shown in Figure 2.

P6 predecessor and successorFigure 2

There are four relationship types to choose from in Primavera P6:

Finish to Start (FS)

The most commonly used relationship is (FS).

For Example:

When build walls have Finished the installation of the roof can Start, as shown in Figure 3.

Finish to Start RelationshipFigure 3

Start to Start (SS)

SS is used to describe a starting dependency between tasks.

For example:

The Site work activity cannot Start Until Safety Management Starts, as shown in Figure 4.

Start to Start RelationshipFigure 4

This type of activity is commonly used with Start milestones, as shown in Figure 5.

AStart To Start RelationshipFigure 5

Finish to Finish (FF)

FF is used to describe a Finishing dependency between tasks. One activity cannot Finish until another activity Finishes.

For example:

Project Management cannot Finish until the site work is Finished, as shown in Figure 6.

Finish To Finish RelationshipFigure 6

This relationship is commonly used with Finish Milestones, as shown in Figure 7.

Relationship Types in Primavera P6Figure 7

Start to Finish (SF)

This is a somewhat confusing relationship type and is the least used of all the activity relationships. It states that an activity cannot Finish until its’ successor Starts, as shown in Figure 8

Relationship Types in Primavera P6Figure 8

Most Industry best practice guidelines actively discourage its’ use. There are very few examples of a truly, practical purpose for this relationship therefore we recommend that you avoid using it, as shown in Figure 9.

Start to Finish RelationshipFigure 9

Summary

A large part of the success of any project is predominantly achieved by adhering to a realistic and accurate schedule that makes logical steps through the network. Building a schedule that is transparent by using the FS relationship will represent the sequence of activities realistically.

SS and FF relationships are used, but they are usually tied to Start and Finish Milestones.

The SF relationship does exist in Primavera P6, but owing to its confusing nature it is very rarely used. We wholly recommend, along with most Project Management guidelines, that this relationship is not used.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2022 · Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us