• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Site-Logo
Phone 703-910-2600

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Planned Value and Earned Value: What’s the Difference?

You are here: Home / Earned Value Mgmt / Planned Value and Earned Value: What’s the Difference?

November 10, 2021 By Ten Six

Planned Value and Earned ValueWhat is the difference between Planned Value (PV) and Earned Value (EV)? If you’ve got team members asking you this, or you are trying to work it out for yourself, look no further!

In this article, we’ll answer the question: “How do you calculate EV and PV?” and give you a worked example for both so you can see how to use these formulas in practice.

Planned Value (PV)

One of the first things you’ll do when you get started with earned value management calculations is to work out the Planned Value (PV). This is the value of the work that is due to be carried out on the project, based on the activities from the project schedule.

It’s a financial figure, so although we’re talking about ‘value’ what you are measuring is a monetary amount which equates to the approved project budget for an activity or work breakdown structure  component. It’s usually used to represent the cost of part of the project because the PV for the whole project is the same as the Budget at Completion, so we tend to use BAC to talk about the whole project.

You’ll also hear it referred to as Budgeted Cost of Work Scheduled (BCWS) which is perhaps an easier term to use when explaining it to other people, although most of the textbooks now stick with PV.

PV is calculated at the beginning of the project, before the work is carried out. It becomes your financial baseline.

How to Calculate Planned Value

Formula: PV = task budget x percent complete

Simply multiply the amount of work complete (or planned to be complete at any given point) by the budget for the work. When a task is 100% complete, the PV will equal 100% of the budget for that activity.

Worked Example: Planned Value

Let’s say you have a project with a duration of six months. The project’s budget is $60k. You are three months into the project and the client asks you to update the earned value management numbers (whoops – you should have been on top of this!). The team is halfway through the work so 50% of it should have been completed.

The client asks you to send them the PV.

We know that PV is the financial amount equivalent to the work that should have happened according to the schedule. We do not need to take into account any actual progress or performance at this time.

PV = 50% of $60k

PV = $30k

OK: it’s a little bit odd for a client to be requesting the PV numbers, because they are used to calculate schedule variance and Schedule Performance Index (SPI) which are more useful to know, but hopefully that illustrates the calculations!

Earned Value (EV)

Next, we come to Earned Value (EV). It’s the value of the work that has actually been completed, so this is where project performance comes into play. No longer are we working out monetary figures against the baseline – we’re dealing in the cold, hard world of reality and what the project team has managed to get done.

Consequently, we should expect EV and PV to be a little bit different, knowing what we do about how changes and circumstance affect a team’s ability to be able to deliver exactly to schedule!

Earned Value represents what you have got for the investment in the project so far and can help you spot trends. You’ll also hear it referred to as Budgeted Cost of Work Performed (BCWP), which is a good way of explaining it to people new to the concepts of EVM, although it is slightly old-fashioned nomenclature.

How to calculate Earned Value

Formula: EV = BAC x % complete

You work out EV by multiplying the percent complete for the work package or project as a whole by the budget for the task.

Worked Example: Earned Value

Let’s use the same project. It has a duration of six months, a budget of $60k and you’ve been working on it for three months. However, you are running behind plan and the client is getting concerned. They want an EV report to quantify the situation.

When you look into project performance, it is worse than you expected and only 30% of the work has been completed. You know you should be at 50% because you are halfway through the project. So what is the project’s EV?

EV = 30% of $60k

EV = $18k

This is not good news to the client and you start to think about ways to get the project back on track. You dive deeper into the numbers and use the EV to work out the schedule and cost variances, SPI and Cost Performance Index (CPI).

If the calculations are starting to sound a bit tricky, do not worry. Earned value management software can do a lot of the heavy lifting for you and create tailored reports so you have real-time data at your fingertips without having to get out your calculator.

Both these calculations are covered and explained in our earned value management training.

The differences between EV and PV

As you’ve seen, the main difference between Planned Value and Earned Value is that Planned Value does not take actual performance into account. That doesn’t make it less useful: it is the baseline figure against which you can compare actual performance.

EV gives you a general overview of how the project is doing, but you’ll want to dig into the other calculations and the context behind the project’s performance to get the full picture about any variances and why they are happening.

EV tools can help with presenting and interpreting the data in the fastest way, so as long as your software is set up to support you in data analysis, you’ll be able to draw conclusions from your numbers to take the appropriate action.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2023 Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us