• Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Customized Video Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • Consulting
      • RFP Support
      • Your EVM System
      • Certification
      • Data Analysis and Reporting
      • Post Contract Support
      • Staff Augmentation
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Contact Us

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk

You are here: Home / Deltek Acumen / Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk

July 13, 2018 By Ten Six

Let’s say your project has the potential to incur a procurement delay that jeopardizes project completion. How can Deltek Acumen Risk help you consider a mitigation effort to reduce the impact of this procurement delay?

Deltek Acumen Risk provides a Monte Carlo simulation that calculates probability distributions of project completion based on numerous iterations of the project schedule. The Monte Carlo analysis may consider both duration uncertainty and risk events. In this way a duration accuracy sensitive and risk adjusted schedule is possible.

And this provides a more complete picture of the true project situation. But the story may not end here. Efforts to mitigate risk events may also be included in a Monte Carlo analysis. Mitigation may incur additional cost and time, but the reduced impact of a negative risk event may be paramount.

This article demonstrates how to include a mitigation effort using the  Deltek Acumen Risk Monte Carlo analysis.

Our demonstration Primavera P6 Professional schedule is displayed in Figure 1.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 1Figure 1

This is a short pipe inspection and repair project. The pipe is first inspected. Then the required adapters are ordered. Finally, the pipe is repaired. The pipe and adapter installation is dependent on arrival of the adapters. Any significant adapter procurement delay has a direct negative impact on schedule completion.

We want to run a Monte Carlo analysis of our schedule so we import the Primavera P6 schedule into Deltek Acumen Risk. Figure 2 shows the imported schedule.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 2Figure 2

Before we run a Monte Carlo analysis we run a schedule quality analysis on the schedule to confirm it is agreeable for a Monte Carlo analysis. Figure 3 presents a report on the schedule quality.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 3Figure 3

Our pipe inspection and repair project has received an overall schedule quality score of 93%, which is really good. We are ready for a Monte Carlo analysis.

We continue and select the S3 // Risk tab. Once we are in the Risk tab we select right panel | risk register, Figure 4, to replace the Gantt chart on the right with a risk register from the Views area of the risk Ribbon.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 4Figure 4

Figure 5 displays the risk register.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 5Figure 5

In Figure 5 we select the risk matrix icon to confirm our probability schedule impact range. Figure 6 shows the probability and impact ranges.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 6Figure 6

Our probabilities are fine, but the schedule range requires adjustment to the values displayed in Figure 6. This adjusts the range of schedule impact to fall in line with our short schedule. It is beyond the scope of this article to consider cost impact. All cost impacts are set to negligible so these cost values require no adjustment.

After inspecting our risk register we proceed with a Monte Carlo analysis. Note that the duration uncertainty is set to very conservative. In Figure 7 we select to run uncertainty only (no risk events).

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 7Figure 7

With our very conservative duration uncertainty setting we would expect our schedule to meet or beat duration estimates. We then run the Monte Carlo analysis and receive the report displayed in Figure 8.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 8Figure 8

As expected our schedule met the April 28, 2020 deterministic project end date.

Continuing we run a Monte Carlo analysis, including both uncertainty and risk events, Figure 9.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 9Figure 9

The results are reported in Figure 10.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 10Figure 10

This time the April 28th, 2020 end date was achieved on 55% of the iterations. And the worst case scenario is May 11th, 2020. Risk events are demonstrating a noticeable negative impact on schedule completion. This is not good, but highly probable given our risk events. We save the data for comparison by selecting the ‘add to risk comparison’ icon, Figure 11.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 11Figure 11

To expand the risk register we first set the right panel to none, Figure 12.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 12Figure 12

The left panel is set to risk register, Figure 13.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 13Figure 13

The risk register, including mitigation, is now fully visible, Figure 14.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 14Figure 14

Enable the mitigation of the procurement delay risk event, Figure 14. To mitigate the procurement delay risk event we choose to pay $200 to expedite adapter delivery. Enter $200 for the cost of quick delivery, Figure 15.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 15Figure 15

The probability, schedule, and cost mitigation values are those that the risk event values become as a result of the mitigation effort. So it’s not the probability of mitigation occurring, but an adjusted procurement delay risk event probability. The probability reduces from very high to low. The schedule impact reduces from high to very low or zero day’s impact, Figure 16.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 16Figure 16

Return to the previous view by selecting right panel | activities, Figure 17.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 17Figure 17

Now we set the Monte Carlo analysis to include uncertainty, risk events, and mitigation, Figure 18.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 18Figure 18

The analysis report is displayed in Figure 19.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 19Figure 19

Observe from the metrics that this mitigation had a noticeable positive effect on schedule compression. Select add to risk comparison, Figure 20, to include these results in our risk comparison.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 20Figure 20

Continue and select right panel | risk exposure comparison, Figure 21.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 21Figure 21

The final comparison is displayed in Figure 22.

Modeling Risk Event Mitigation Efforts in Deltek Acumen Risk Fig 22Figure 22

This is a graph of the Monte Carlo results S-plots. Plotted are the duration uncertainty & risk events verses the duration uncertainty, risk events, and mitigation. At 80% confidence the variance between the no mitigation and mitigation adjusted schedules is 4-days, which is significant for our short project. The procurement delay mitigation efforts are well worth the effort.

Summary

Deltek Acumen Risk provides an efficient Monte Carlo analysis feature. After risks have been entered in the register and mapped to specific activities, it is possible to run a Monte Carlo analysis of the risk adjusted schedule. Enter a mitigation effort to reduce the probability of the risk event occurring and also minimize the schedule impact if it does occur.

An analysis including mitigation is then feasible. Compare the risk adjusted and mitigation adjusted schedules in a risk exposure comparison graph. Examine the variance at your desired confidence percentage, most typically, 80%. In this way project managers can investigate the value of risk event mitigation efforts.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
  • Uncategorized
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • Clients
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2022 · Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Customized Video Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • Consulting
      ▼
      • RFP Support
      • Your EVM System
      • Certification
      • Data Analysis and Reporting
      • Post Contract Support
      • Staff Augmentation
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Contact Us