Financial Periods in P6
Updating your schedule can cause P6 to recalculate your historical data across an extended timeline, but financial periods in P6 freeze that data against future changes. Let’s take a look.
A financial period in P6 is a named time bucket, such as a fiscal month or quarter. In P6, these periods lock down actual cost and unit data at the end of each reporting cycle. This ensures you can look back and see exactly what happened without future updates shifting your numbers. P6 typically rewrites historical data due to:
- Dynamic Linear Smoothing – P6 treats activity cost as a pool of data spread over time. For example, extending a 4-month activity with $32,000 in actual costs to 8 months will redistribute that $32,000 across all eight months ($4,000/month), rewriting the initial 4-month spending history.
- The “Recalculate Actual Units and Costs” setting – When this setting in the Projects | Details | Calculations tab is toggled on, any adjustment to remaining duration or duration percentage complete forces P6 to overwrite your manually entered historical actual costs.
- Changing the Resource Price Per Unit Mid-Project – If you modify a resource rate, P6 will retroactively apply the new cost rate to actual units already completed in the past unless you have frozen those past periods.
- Out-of-Sequence Progress – When a downstream task is progressed before its predecessor finishes, rescheduling shifts the uncompleted portions of the task. If actual costs are associated with that task’s resource assignments, this shift creates a new cost distribution and alters historical reporting data.
Financial periods in P6 resolve these issues by storing period actuals, locking actual costs within a specified date range once the period closes. They also enable past period reporting to drive ‘Past Period Actuals’ columns in your layout. Together, this allows you to build your project’s true S-curves, period-by-period cost reports, and earned value trend charts.
This article demonstrates how to create financial period batches, store period performance after each update and display period-by-period cost data in your P6 layouts.
The core idea: Financial periods are snapshots. They freeze your cost and resource actuals at a point in time, period by period, so your reports stay consistent and auditable..
Process Overview
Master the workflow by following these four fundamental steps:
- Define the Financial Period Batch – Create a new batch or modify an existing one to establish your time intervals and how they are divided (weeks, months, quarters, or custom fiscal cycles).
- Assign the Batch to Your Project – Link your customized financial period intervals to your specific project settings.
- Store Period Performance – Run the application’s performance storage utility after every routine schedule update to permanently lock in your data.
- Display Period Data in Your Layout – Add the past period actual columns or time-phased spreadsheet fields to your activity views to report your findings.
Demonstration
Let’s walk through each major step in more detail with a demonstration. We have in Figure 1 our demonstration schedule baseline.
Define the Financial Period Batch
To define the batch, Figure 2, we choose Admin | Financial Period Calendars


Our reporting period is monthly. Since there already is a Monthly Calendar defined, we choose to modify it, Figure 3.

Figure 4 displays the Batch Create Financial Periods dialog.

When creating the project schedule’s financial periods, a screenshot of the original batch setup was not saved. Figure 4 displays a recreation of the dialog box prior to batch execution. Because the ‘Last Period End Date’ field is automatically populated by P6 and cannot be edited manually, a text box was added to the image to accurately reflect the calendar year used during the actual setup.
Our demonstration schedule is for the year 2036, so we create a batch, Figure 4, for the duration of that year: Batch Start Date 01-Jan-2036 and Batch End Date 31-Dec-2036. Our project reports monthly, so the Financial Period is Every 1 Month.
After defining our interval and divisions, we click Batch Create, Figure 4. You will immediately receive a warning.

Once you create the batch, there is no going back to delete, hence the warning message. And if successful, you will receive the following message, Figure 6.

That is it! Our batch for the year 2036, with monthly intervals, has been created.
Pro tip: Create all your financial periods for the full project lifecycle upfront — even future ones. It’s far less hassle than creating them retroactively mid-project when you’re already under pressure..
Assign the Batch to Your Project
This next step is easy to forget, but can be very frustrating after you update your schedule and find that you stored all your period performances in the wrong Financial Period Calendar. Follow these steps to make sure you store to the correct Financial Period Calendar.
Click the Projects | General bottom details tab, then confirm the Financial Period Calendar is appropriate for your schedule. In Figure 7, we need to update the Financial Period Calendar.

Click the ellipse for the Financial Period Calendar field in Figure 7. Then, in the Assign Financial Period Calendar, choose the Monthly Calendar and click Select, Figure 8.

Figure 9 displays the Projects | General tab with the correct Monthly Calendar Financial Period Calendar.

Caution: Setting the Financial Period Calendar is straightforward but easily overlooked. Assigning the wrong calendar will cause P6 to store your period performance in the wrong financial buckets, permanently corrupting your historical data and monthly cash flow metrics. Always verify this setting before running the Store Period Performance utility.
Store Period Performance
The next step is to update your schedule. For a primer on progressing a P6 Professional schedule, refer to the following article:
In Figure 10, we have our demonstration schedule ready for updates.

Note in Figure 10 that the duration type of all non-milestone tasks is Fixed Duration & Units; this is a time-constrained and cost-constrained project.
In Figure 11, the status for the first month’s reporting period data is entered, and we are about to schedule the project.

We set the data date in Figure 11 to the beginning of the next reporting period, February 1, 2036. Next, in Figure 11, click Schedule.
Figure 12 displays the schedule after the first reporting-period update in January 2036.

After our update, we then choose Tools | Store Period Performance, Figure 13.

This brings up the Store Performance Period dialogue, Figure 14.

Make sure the Financial Period field displays the beginning of the reporting period, Figure 14, and make sure the Data Date is set to the beginning of the next reporting period. Then click Store Now, Figure 14.
That’s it! The January 2036 performance period is frozen.
Heads Up: Store Period Performance should only be run once per period, after all actuals for that period have been entered. Running it multiple times can cause data inconsistencies. Make this part of a controlled end-of-period checklist..
Display Period Data in Your Layout
Now we need to tell P6 Professional what financial period data to make available for reporting. Choose Edit | User Preferences and follow these Figure 15 steps:
- Choose the Application tab.
- Click the Select button.
- Set the Start Date.
- Set the End Date

Figure 16 displays the proper Financial Period Data start and finish dates for our schedule.

Because of the steps we performed in Figures 15 and 16, the Financial Period Value parameters are available to select in the Columns feature, Figure 17.

Figure 18 shows the current Earned Value (EV) data and the first month’s stored performance period, which match.

Figure 19 displays the current EV data and the second month’s stored performance period.

Figure 20 displays the EV data for the current and third month’s stored performance period.

Figure 21 shows the final EV data, current and the final month’s stored performance period.

As shown in Figures 18 through 21, the current Earned Value data matches the Financial Period Value only during the initial month. Because the project-life metrics track cumulative progress while the financial period metrics capture isolated monthly intervals, the values naturally diverge starting in the second period.
A few things to watch out for
Financial periods in P6 are defined at the global level, not at the project level. That means the same set of periods applies across all your projects in the database, which is great for consistency, but means you need a single agreed-upon reporting calendar across your organization. If different project teams are on different cycles, things get messy fast.
Also worth knowing: the financial period calendar assigned to a resource or role determines which period buckets their time-phased data rolls into. Make sure your resources have the correct calendar assigned before you start storing periods, or the distribution might not line up the way you expect.
Workflow tip: Build “Store Period Performance” into a formal end-of-month checklist alongside your schedule update, progress reporting, and baseline management steps. It takes about 30 seconds to run but makes a huge difference to report quality over time..
The two most common mistakes
These two mistakes recur on real P6 projects. Learning them now saves you a lot of pain later.
Mistake 1: Skipping Store Period Performance at month-end
This is the most common one. Teams treat financial periods as optional admin noise, get busy at month-end, and skip running Store Period Performance. The problem is that once you miss a period, you can’t retroactively rebuild that locked snapshot cleanly. Your historical data for that window is permanently dynamic — meaning it can silently change if anyone touches actuals later.
Fix: Make Store Period Performance a non-negotiable step in your end-of-month reporting process. Put it on a checklist, assign it to a named person, and treat it with the same seriousness as submitting your progress report.
Mistake 2: Not creating periods far enough in advance
The second most common mistake is setting up financial periods only as you need them, one at a time, reactively. This leads to scrambling at the start of each reporting cycle, and sometimes results in periods being created with slightly wrong dates, which then corrupts your time-distribution data.
Fix: At project kickoff, create a full year’s worth of financial periods, or better yet, periods for the entire project duration. It takes about five minutes and eliminates a recurring source of month-end stress..
Summary
Maintaining a secure data audit in P6 Professional is challenging because schedule updates, salary changes, and out-of-sequence work can retroactively shift historical numbers.
Implementing Financial Periods in P6 solves this by locking actual costs into specific date ranges once closed. This feature ensures historical data integrity, giving teams reporting confidence when displaying current-period store performance alongside current project data.
This also lays the foundation for true-to-schedule S-curves and other EV trend charts.
TL;DR Financial periods in P6 = time-bucketed, locked actuals. Create them in Admin → Financial Periods, close them with Store Period Performance at month-end, and report on them using Past Period columns in your layouts. Avoid the two big mistakes: don’t skip month-end storage and create your periods upfront..