Driving Relationships in P6 Explained
When a critical task has multiple predecessors, you need a quick way to find the specific task threatening your start date. Let’s take a look at this in P6.
In Primavera P6, a driving relationship occurs when a predecessor directly determines the start or finish date of its successor. While you can find this by inspecting an individual activity’s relationships, doing so manually on large-scale projects is highly inefficient.
A red Gantt chart bar warns you that an activity is critical, but it fails to show you which specific predecessor is causing the restriction. Relying on the ‘Driving’ check box or trace feature provides the exact insight needed to isolate the true bottleneck.
The purpose of this article is to show schedulers how to pinpoint driving tasks, allowing them to instantly isolate the predecessors dictating a critical effort’s timeline.
Driving relationships are the specific predecessor connections that directly control an activity’s Early Start (during the forward pass) or its Late Finish (during the backward pass). When a predecessor is driving, any delay to that predecessor delays the successor by the exact same amount. The activities are effectively chained together with zero free float between them at that link.
When an activity has multiple predecessors, only one (or occasionally more than one in a tie) will be the driving predecessor at any given point. The others are non-driving. That is, they have some free float relative to the driving predecessor and wouldn’t immediately affect the successor’s dates if they slipped slightly.
A non-driving predecessor would produce an earlier date for B if the formula were applied. Meaning B could start or finish earlier than the predecessor requires. The driving predecessor is always the one creating the tightest constraint.
The Driving Predecessor Column in P6
Adding the column
Follow these steps to view which predecessor or successor is a driving task. Choose the Activities page (Project | Activities) and in the bottom details select the Relationships tab, Figure 1.

In the predecessor frame, right-click (star stamp number 1) on any column header and choose Customize Predecessor Columns in the pop-up menu. Then, in the Predecessor Columns dialog box, navigate to the General category, select the Driving option, and click the right arrow button to add Driving to the Selected Options, Figure 2, and click the OK button.

Repeat, add a Driving Column, but for the successor frame. Figure 3 displays the schedule with task E selected in the Activity table.

This shows the Activity ID of the predecessor currently driving the selected activity’s Early Start. In Figure 3, task E has three predecessors; we quickly see from the bottom details that activity B is the driving task of task E.
Driving relationship indicators in the Gantt
P6 Professional allows you to turn display relationship lines on or off. To locate this setting, right-click on the Gantt chart (star stamp labeled one), then choose Bar Chart Options from the pop-up menu, Figure 4.

Continuing, in the Bar Chart Options dialog box, confirm or toggle on Show Relationships, Figure 5.

The Gant view has only four hardcoded visual states for its lines:
- Solid Red: Critical Path (always driving)
- Solid Black: Non-critical, but driving
- Dotted Black: Non-critical, non-driving
- Solid Blue: A line you have currently clicked on and selected.
Figure 6 displays a Gantt chart with a visual representation of each relationship line.

💡 Non-driving relationships are not redundant. A non-driving predecessor currently has free float relative to the driving predecessor, but it can become driving if the current driver accelerates or if the non-driving predecessor slips. Removing a non-driving relationship because it’s not currently governing removes a genuine logic constraint from the schedule..
Forward Pass vs Backward Pass Driving
Driving relationships work in both directions in the CPM calculation, and understanding both is important for complete schedule analysis.
| Direction | Driving Element | What It Controls | Used to Answer |
| Forward pass | Driving predecessor | Activity’s Early Start / Early Finish | Why can’t this activity start sooner? Which upstream activity must be accelerated? |
| Backward pass | Driving successor | Activity’s Late Finish / Late Start (and therefore Total Float) | Why does this activity have so little float? Which downstream commitment is driving the late dates? |
In a burst point (one predecessor, many successors), the driving successor is the one on the critical or near-critical path, the downstream activity giving the predecessor the least float.
Trace Logic: Following the Driving Path
Opening Trace Logic
Right-click any activity in the Activity Table or Gantt chart and select ‘Trace Logic’. P6 opens a separate pane showing the selected activity in the center, predecessors to the left and successors to the right. Each activity shows its early and late dates, as well as its total float. Figure 7 displays the schedule with activity E selected in the activity table and the trace logic in the bottom view.

Reading the driving chain
As in Figure 6, driving relationships are shown as solid black (driving, non-critical), red (driving, critical), or dotted black (non-driving, non-critical) in Trace Logic, Figure 8.

To trace the driving path back to its origin, select in Figure 8 the driving predecessor to task E in the Trace Logic view, task B, and the view re-centers on that activity, showing its own predecessors. In Figure 8, we click on task B, the driving predecessor of task E. Figure 9 displays the resulting network diagram with task B at the center.

Repeat until you reach the project start, a constraint or an activity with actual progress that’s driving the chain.
💡 When you trace a driving chain backward, and it terminates at an activity governed by a finish constraint (such as a ‘Finish On or Before’ milestone), you have found the target driving that chain’s negative float. This is critical for recovery planning: you must focus acceleration efforts exclusively on this specific upstream driving chain to pull the completion date back and eliminate the negative float..
Using Driving Relationships for Recovery Analysis
When an activity or milestone is behind schedule, the driving relationship chain tells you precisely where the recovery effort will have an effect. Effort applied to a non-driving predecessor is wasted from a schedule perspective, as it won’t improve the activity’s forecast date.
Step 1 — Identify the driving predecessor
Use the Driving Predecessor column or Trace Logic to confirm which predecessor is currently setting the late activity’s Early Start. Check the relationship type (FS, SS, FF, SF) and the lag. This tells you both which predecessor to target and how much it needs to improve to recover the late activity.
Step 2 — Quantify the required recovery
The Finish Variance for the late activity indicates how many days of recovery are needed. If the activity needs to recover 8 days and the driving predecessor has a Finish Variance of 8 days with zero float, the driving predecessor must be recovered by exactly 8 days. This could be achieved by crashing, fast-tracking or relaxing constraints to bring the late activity back to baseline.
Step 3 — Check whether recovery propagates
After identifying the driving predecessor, use Trace Logic to check whether it’s being driven by a further upstream activity. Recovery must be applied at the true root cause. Recovering an intermediate activity without addressing its own driving predecessor won’t achieve the required dates.
Table 1 – Recovery Table
| Recovery Action | Effect on Driving Path | Effect on Non-Driving Path |
| Reduce the duration of driving predecessor | Directly improves the successor’s Early Start by the same amount | No effect on non-driving predecessors’ governance |
| Reduce lag in the driving relationship | Directly improves the successor’s Early Start by the exact amount the lag is reduced. | No effect on non-driving lags |
| Reduce the duration of the non-driving predecessor | No effect on the successor’s Early Start | No effect |
Driving Relationships in Baseline Comparison
Comparing the current driving predecessor against the baseline driving predecessor is a useful forensic tool. When a different predecessor drives an activity compared to the baseline, it indicates that the driving path through that specific activity has shifted, which may or may not alter the project-wide critical path. This shift signals that a completely different upstream chain of work is now governing the activity’s dates.
This shift in driving relationship is often a precursor to a delay claim. A contractor may argue that a client-controlled activity (which was non-driving at baseline) has become the driving predecessor due to delay on the client side. Documenting the baseline driving predecessor and tracking when it changes is essential evidence in a time impact analysis.
⚠️ In each update cycle, review any critical or near-critical activities in which the driving predecessor has changed from the previous period. Record the change, the reason and the impact in the schedule narrative. A driving relationship change that shifts responsibility from one party to another can be a commercially significant event and must be documented..
Driving Relationships and the Longest Path
P6 offers a ‘Longest Path’ filter (Tools | Schedule | Options > Define critical activities as) as an alternative to the standard zero-float critical path. The Longest Path traces the sequence of driving relationships from the start to the project’s finish. This is the chain with the longest total duration, regardless of float values or constraints.
The Longest Path and the zero-float critical path often coincide, but they can diverge when:
- Hard constraints (Mandatory Finish (MF), Mandatory Start (MS)) fix dates and suppress negative float, masking the true longest chain.
- Multiple calendars cause the zero-float path to follow a different chain than the longest calendar-day path.
- Near-critical chains have zero float due to constraint interaction but aren’t on the longest logical path.
When the two differ, the Longest Path is generally the more reliable indicator of what’s truly driving the project end date. The longest path is preferred for schedule optimization and forensic delay claims, but final contract submissions should be set to Total Float less than or equal to zero. This ensures your final schedule flags both the project-driving activities (the Longest Path) and any localized paths that risk missing intermediate contractual milestones.
Summary
The Driving column in the bottom details relationships tab and the Trace Logic tool are the most efficient ways to identify true driving predecessors and map delayed chains upstream to their root cause.
When creating recovery plans or updating schedules, you must focus directly on these driving tasks, as progress can frequently shift the driving path to entirely new activities. The Longest Path traces the sequence of driving relationships from the start to the project’s finish and is the chain with the longest total duration.
In forensic delay analysis, documenting the baseline driving predecessor and tracking its changes over time are critical. This analysis provides the primary evidence required to successfully substantiate Time Impact Analyses (TIA) and Extension of Time (EOT) claims.