• Skip to primary navigation
  • Skip to main content
  • Skip to primary sidebar
  • Skip to footer
Site-Logo
Phone 703-910-2600

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us
  • Training Classes
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    • Primavera P6
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Creating a Risk Register in Microsoft Project

You are here: Home / Microsoft Project / Creating a Risk Register in Microsoft Project

May 2, 2018 By Ten Six

Microsoft Project does not have a risk event register feature, but with a little effort you can create a risk register in Microsoft Project.

Projects are a risky proposition. And it’s the unique nature of projects that make them particularly risky ventures. Project Managers have one go or opportunity to get everything right on a project. It makes sense that proficient project managers consider what potentially could go wrong. Duration estimates may have been overly optimistic. Weather may be a factor. Other risk events may be realized.

Well, project managers need a way for identifying and categorizing risk events for appropriate action. In Microsoft Project it is possible to create a risk register table that maps potential risk events to activities, along with their probability and impact. In this way project managers can quickly identify and rate risks related to activity efforts.

This article demonstrates the steps required to create a risk register table in Microsoft Project.

We have in Figure 1 our demonstration project.

Creating a Risk Register in Microsoft Project Fig 1Figure 1

This is a small Pipe Inspection & Repair project. Some risk events that may occur on this project include procurement delays for the order and delivery of adapters, the delivered adapters may be sized wrong and not fit properly, and the quality assurance inspection may have a long list of checklist items to correct before acceptance. Project managers need a way to identify and analyze these potential risk events. The risk register supports the spotting and evaluation of project risk events.

Creating a risk register table is all about custom fields. To begin the process of generating a risk register table select Project | Custom Fields, Figure 2.

Creating a Risk Register in Microsoft Project Fig 2Figure 2

In the custom fields dialog highlight Text1 and rename it, Risk, Figure 3.

Creating a Risk Register in Microsoft Project Fig 3Figure 3

Add another text field named Probability and select the lookup custom attributes, Figure 4.

Creating a Risk Register in Microsoft Project Fig 4Figure 4

Add menu values 1 to 5, Very Low to Very High, Figure 5.

Creating a Risk Register in Microsoft Project Fig 5Figure 5

Do the same for an Impact text field. Add a Risk Level field and select the formula custom attribute, Figure 6.

Creating a Risk Register in Microsoft Project Fig 6Figure 6

In the formula dialog, Figure 7, insert the probability field.

Creating a Risk Register in Microsoft Project Fig 7Figure 7

Continue and add a multiplier and impact field. Figure 8 displays the final Risk Level equation.

Creating a Risk Register in Microsoft Project Fig 8Figure 8

We have one more field to define, a Risk Warning Indicator, text field. In the custom fields dialog, rename Text5, Risk Warning Indicator. Select the formula custom attributes, Figure 9.

Creating a Risk Register in Microsoft Project Fig 9Figure 9

Enter the equation in Figure 10.

Creating a Risk Register in Microsoft Project Fig 10Figure 10

This formula identifies a risk level as very high, medium, or very low. After inserting the formula select graphical indicators, Figure 11.

Creating a Risk Register in Microsoft Project Fig 11Figure 11

Then insert the three indicators displayed in Figure 12.

Creating a Risk Register in Microsoft Project Fig 12Figure 12

Add the five text fields to the activity table, Figure 13.

Creating a Risk Register in Microsoft Project Fig 13Figure 13

And add the potential risks to the risk register table. If there is no risk, leave the risk field blank and set both the probability and impact to 1.

The final schedule, including identified and categorized risks is displayed, again, in Figure 13. Our risk register warns that a procurement delay is a high level risk and may have a possible significant negative impact on the schedule. We may want to arrange and pay for quick delivery of the adapters to mitigate this risk. Also, the delivered adapters may not match the piping, a medium risk, because the likelihood is low. We will want to make sure the planner consults the pipe fitter and confirms the adapter model before ordering.

Finally, the quality assurance inspection is always a potential risk. We will want to thoroughly test the piping and make certain the work site is clean before final inspection. It is usually the small neglected items that become an issue during the quality assurance inspection. And are a drag on project completion.

After creation of your risk register you most likely want to leverage your risk table for other project schedules. Select View | Tables and Save Fields as a New Table, Figure 14, to save your risk register table formatting.

Creating a Risk Register in Microsoft Project Fig 14Figure 14
Creating a Risk Register in Microsoft Project Fig 15Figure 15

In Figure 15 we simply enter the name, risk register, and save as a new table. Then we are done. Risk register now appears in the list of available tables for the Pipe Inspection & Repair project, Figure 16.

Creating a Risk Register in Microsoft Project Fig 16Figure 16

To copy the risk register table to another project consult the following article Copying Tables Between Projects In Microsoft Project.

Summary

A thorough project management effort will include an investigation of project risk. Microsoft Project does not, per say, have a risk register. However, it does have all the functionality needed to create a risk register table. After generation of a risk register save the table for other project schedules. In this way risk assessment will become a common and valuable fixture in the project management effort.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management
CONTACT US

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals
Primavera P6 EPPM Fundamentals
Primavera P6 EPPM Administrator
Primavera P6 BI Publisher Fundamentals
Deltek Cobra Fundamentals
Deltek Cobra Advanced
Deltek Acumen Fuse
Deltek Acumen Risk

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter
  • Consulting Services
  • About Ten Six
  • Contact Us
  • Blog

Copyright © 2023 Ten Six Consulting, LLC · 703.910.2600

  • Training Classes
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Earned Value Management Training
    • Project Management Training
    • Open Training Class Dates
  • Scheduling Services
  • Earned Value Mgmt. Services
    ▼
    • RFP Support
    • Your EVM System
    • Certification
    • Data Analysis and Reporting
    • Post Contract Support
    • Staff Augmentation
    • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
  • Tools
    ▼
    • Primavera P6
      ▼
      • Knowledge Transfer, Mentoring and Coaching
      • BI Publisher Services
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Knowledge Transfer, Coaching and Mentoring
      • Staff Augmentation
    • Microsoft Project to Primavera P6 Conversion Services
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us