You may think that your project is current in the database after performing any kind of change or schedule update, and for almost all intents and purposes – it is. However, many of you may not be aware that other users could run a report on your project that doesn’t have the most
Task Location and Microsoft Project to Primavera P6 Translations
A common problem that is faced when converting a schedule from Microsoft Project to Primavera P6 is that the translation process moves the project tasks from the order they were in previous to the translation
Pay Rates in Primavera P6 Professional
What if your company wants you to provide different project costs depending on whether the associated report is an internal or external report? Do you know how to create different pay rate types in Primavera P6?
Primavera P6 Personal Resource Calendars
A common challenge for managers is keeping track of the availability of resources assigned to their projects. This may become particularly difficult during the summer months when resources typically go on vacation
Assigning a Project Specific Material Expense in Primavera P6 EPPM
In Primavera P6 EPPM, resources are great for assigning labor, non-labor and material generic resources to a schedule. However, if you have a subcontractor doing all the work on a task at a fixed price
Primavera P6 Gantt Chart Attachments
Primavera P6 has a rather involved process of adding notebook topics to the Gantt chart, but if you are looking for a quick way to annotate the Gantt chart then read on.
Using Pay Rates in Primavera P6 EPPM
Your company may have different pay rate schedules depending on whether your resources are working on an internal project or an external project. Primavera P6 Enterprise Project Portfolio (EPPM) has a useful feature that allows you to define more than one pay rate type.
Using Project Constraints In Primavera P6 EPPM
It is best to avoid project constraints, however, sometimes they can describe the importance of a constraint that cannot be ignored. If this is your situation, than you want to become familiar with the procedure
Primavera P6 And Deltek Cobra On A Tablet
For a while now I’ve been looking out for a Windows based tablet powerful enough to run such business tools as Deltek Cobra and Primavera P6 Professional; both of which I teach as part of my job and must have with me wherever I go. And after years of
Tracking Labor Units on Multiple Resourced Activities In Primavera P6
If you have activities with multiple resource assignments in your schedule, it’s typical even with the best of schedules that your resources don’t always work the exact hours they were originally planned