• Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    • Project Management
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    • Primavera P6
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us

Using The Expected Finish Date in Primavera P6

You are here: Home / Primavera P6 / Using The Expected Finish Date in Primavera P6

January 18, 2021 By TheP6Pro

Typically, schedulers think in terms of remaining duration for activities when progressing the schedule, but it is also feasible to specify an expected finish date and have P6 calculate the respective activity’s remaining duration.

The physical percent complete type is the most accurate way to show progress on a schedule. However, it does require more data input than the duration percent complete type. The duration percent complete type is the most efficient way to progress a schedule; it takes the activity percent complete input value and automatically calculates the remaining duration.

The physical percent complete type requires the manual entry of remaining duration. This is in addition to the entry of activity percent complete. And deciphering the remaining duration of activities may quickly become a tedious process.

Further, in certain situations it may be simpler to specify an activity finish date. Fortunately, the physical percent complete type provides the option to enter the expected finish date of an activity and have P6 calculate the remaining duration.

This article provides a quick tip to show the utility of the physical percent complete type Expected Finish date option.

Below in Figure 1, we have a Build Block Wall effort that uses a Physical Percent Complete Type.

Expected Finish Date in Primavera P6Figure 1

It has been given a Physical % Complete value of 50%. But note also in Figure 1 that the Build Block Wall remaining duration is still set to 10-days. We need to provide more information based on progress and an estimate of completion.

We have been told by the foreman that the wall is indeed 50% complete. We then ask the foreman his estimate of completion. The foreman replies “We have built half the wall, making good progress, the masons will be finished by Wednesday of next week, so 3-days of work is the estimate.”

It is possible at this juncture to go the usual route and manually update the remaining duration field and recalculate the schedule. But another way to go is to specify the effort’s expected finish date and recalculate the schedule. When we choose this path P6 both updates the schedule and computes the activity’s remaining duration.

Again, in some situations it may be easier to specify an expected finish date instead of counting out days on a calendar to determine the remaining duration of the activity.

We proceed and specify a date in the Expected Finish date field, Figure 2.

P6 Expected Finish DateFigure 2

By entering the June 24th and rescheduling, P6 has calculated 3 days of remaining work, Figure 3.

Primavera P6 rescheduledFigure 3

Summary

If a scheduler knows the completion date of an activity, then they can enter this in the Expected Finish date field and reschedule to compute the remaining duration. In this way, the scheduler avoids the sometimes-tedious process of counting out days on the calendar from start date to expected finish date to find the effort’s remaining duration. This simple quick tip may help the scheduler expedite the process of updating the schedule progress.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management

Archives

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals

Primavera P6 EPPM Fundamentals

Primavera P6 EPPM Administrator

Oracle Primavera P6 BI Publisher Fundamentals Training Class

EVMS Training

Deltek Cobra Fundamentals Training

Deltek Cobra Advanced Training Class

Deltek Acumen Fuse Training Class

Copyright © 2021 · Ten Six Consulting, LLC · 703.910.2600

  • Training
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    ▼
    • Project Management
      ▼
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      ▼
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      ▼
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      ▼
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      ▼
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    ▼
    • Primavera P6
      ▼
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us