• Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    • Project Management
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    • Primavera P6
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us

How to Add Activities in Primavera P6

You are here: Home / Primavera P6 / How to Add Activities in Primavera P6

November 23, 2020 By TheP6Pro

How to Add Activities in Primavera P6Here we show you a couple of ways you can add activities in Primavera P6. Activities are typically added to a project using the Activities view in Primavera P6. The activities view is used most frequently during the planning and execution phases of the project.

Upon clicking on the Activities button, as shown below in Figure 1, you are presented with a layout consisting of three separate areas; on the far left is the activities layout, adjacent to this is the Gantt chart and below both of these at the bottom is the Activities Detail area.

Activities button in P6Figure 1

In the Activity table, the Work Breakdown Structure (WBS) elements are displayed as color- coded rows, with each color representing a different level of the WBS, as shown in Figure 2.

Displaying the Work Breakdown Structure in P6Figure 2

To create a schedule, activities need to be added below each element of the WBS. Firstly, you need to select the WBS under which you wish to create your activities. For this project, the first activity will be a start milestone that is located directly below the top level WBS element, ‘New Home Construction.’

There are two options to choose from when adding activities to a schedule in Primavera P6.

Option 1

With option 1, we click on the WBS element ‘New home Construction’ and select the ‘Activities’ button to the right of the Gantt table as shown below in Figure 3.

Activities Button on Gantt Chart in P6Figure 3

We enter a ‘New Activity’ wizard dialog box, where Primavera P6 automatically offers an Activity ID, which is appropriate for a new project schedule. We change the ‘Activity Name’ by typing in ‘Notice to Proceed’ as shown in Figure 4.

How to Add Activities in Primavera P6Figure 4

By clicking ‘Next’ we enter the ‘Work Breakdown Structure’ dialog box. As we have already selected the required WBS before we opened the wizard, it is correctly displaying ‘New Home Construction’ as the WBS element, as shown below in Figure 5. There is an option to select a different level of the WBS by clicking on the ellipse button but as it is correct, we click ‘Next’.

Selecting WBS ElementFigure 5

We enter the ‘Activity Type’ dialog box. The Primavera P6 default for ‘Activity Type’ is ‘Task Dependent’, so from the drop-down menu, we select ‘Start Milestone’ and click ‘Next’ as shown in Figure 6.

Task Dependent Activitiy in P6Figure 6

In the ‘Dependent Activities’ dialog box, we have the option to define the activity’s relationship to other activities within our project. However, as this is our first activity in the schedule we click ‘Next’, as shown in Figure 7.

Defining a Relationship in P6Figure 7

We enter the ‘More Details’ dialog box where we could begin to add Project Expenses, Activity Codes, or Work Product and Documents associated with our activity. Again, as our activity is a Start Milestone it is not appropriate to add these items to it so we click ‘Next’, as shown in Figure 8.

Start Milestone in P6Figure 8

Finally, we come to the end of the wizard (displayed by Congratulations) and when we click ‘Finish’ our ‘Start Milestone’ appears in the Activity table and on the Gantt chart as shown below in Figure 9.

Adding Milestone in P6Figure 9

Option 2

Using Option 2, activities can be added to the schedule directly in the Activity table. Returning to our example we right-click on our ‘Notice to Proceed’. In the ‘Activity Details’ pop-up box we scroll down and select ‘Add’ as shown below in Figure 10.

Adding Additional ActivitiesFigure 10

A new activity appears in the table below ‘Notice to Proceed.’ Primavera P6 creates an Activity ID. All we need to do is enter a name, so we type in ‘Project Start’ as shown in Figure 11.

New Activity in P6 TableFigure 11

‘Project Start’ is another Start Milestone, therefore we enter the ‘General’ tab in the bottom layout area and change the ‘Activity Type’ from Task Dependent (the Primavera P6 default option) to ‘Start Milestone’ as shown in Figure 12.

How to Add Activities in Primavera P6Figure 12

Summary

Both options are a good way to add activities in Primavera P6. The wizard is excellent for guiding novice schedulers through the process, whereas the right-click option in the Activity table is used more frequently by more experienced schedulers.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management

Archives

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals

Primavera P6 EPPM Fundamentals

Primavera P6 EPPM Administrator

Oracle Primavera P6 BI Publisher Fundamentals Training Class

EVMS Training

Deltek Cobra Fundamentals Training

Deltek Cobra Advanced Training Class

Deltek Acumen Fuse Training Class

Copyright © 2021 · Ten Six Consulting, LLC · 703.910.2600

  • Training
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    ▼
    • Project Management
      ▼
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      ▼
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      ▼
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      ▼
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      ▼
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    ▼
    • Primavera P6
      ▼
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us