• Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    • Project Management
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    • Primavera P6
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us

Best Practices for Activities in Primavera P6

You are here: Home / Primavera P6 / Best Practices for Activities in Primavera P6

November 11, 2020 By TheP6Pro

Check out our latest video at the bottom of this page on Best Practices for Activities in Primavera P6

In Primavera P6, an activity represents work that is required to contribute to the completion a Work Breakdown Structure (WBS) deliverable. An activity has a planned start date, a duration, and a planned finish date. An activity can also have resources such as labor, non-labor, and materials assigned to it, as shown in Figure 1.

Best Practices for Activities in Primavera P6Figure 1

One or more activities can be defined below a WBS element in Primavera P6. These activities represent all the different tasks required to perform a deliverable. In our example in Figure 2 shown below, we can see that there are four activities required to meet our ‘Design’ deliverable.

WBS element in Primavera P6Figure 2

In our previous article ‘Developing a Work Breakdown Structure in Primavera P6’ (you can read that here) https://tensix.com/2020/08/developing-a-work-breakdown-structure-in-primavera-p6/ we used the example ‘ProSearch’. If we return to the same example, on the third level of the WBS, under ‘Build’ our WBS terminates at ‘Interface’ ‘Engine’ and ‘DB Connect’. We need to find activities to describe the tasks to complete these deliverable elements as shown below in Figure 3.

Work Breakdown Structure in Primavera P6Figure 3

Firstly, we focus on the ‘Interface’, our design department has researched the ‘Interface’ process and has produced a requirement document that describes the Search field, Search button and Advanced Search button as well as what capabilities it will offer the user.

The ‘Interface’ must deliver the following capabilities for the Search field:

  1. It must work on the following web browsers (Internet Explorer, Firefox, Google Chrome, and Safari
  2. It must support certain operating systems
  3. It must be predictive text-enabled based upon database index
  4. It must offer a spellcheck capability (if not provided by the browser)

Although these capabilities may technically describe deliverables, they are far too detailed to warrant a 4th level to our WBS. We need to focus on the work required to give the ‘Interface’ the desired attributes.

Depending on how familiar our project team is with the work required to develop a schedule, we may be required to interview the people who will perform the work to understand and help create a realistic account of their process. We may also review historical projects that have similarities to our project and talk to the project teams that implemented successful schedules.  After developing a work schedule, our activities for the ‘Interface’ is shown below in Figure 4.

Best Practices for Activities in Primavera P6Figure 4

When we enter these activities into the Primavera P6 schedule, the first activity (Start Search Interface Development) becomes the ‘Start Milestone’ activity type, identifying it as the planned start date of the deliverable.

The last activity (Deliver Completed Code for Testing) becomes the ‘Finish Milestone’, identifying it as the planned finish date of the deliverable.

The activities in-between the ‘Start Milestone’ and the ‘Finish Milestone’ are known as ‘Task Dependent’ activities. Primavera P6 identifies ‘Task Dependent’ activities as activities that are scheduled using the activities calendar and not the calendars of any resources assigned to it, as shown below in Figure 5.

P6 Task Dependent activitiesFigure 5

Before we entered our activities into the P6 schedule we checked that we had created the activity names by following Scheduling best Practice Guidelines.

Best Practice Guidelines for Activity Descriptions

  1. Use the verb, noun naming technique- describe what you are doing and what you are doing it too. An example of activity names for a different schedule that we used is ‘Design Interface’ and ‘Write Code’, as shown below in Figure 6.

Best Practice Guidelines for Activity DescriptionsFigure 6

  1. Keep the description as short as possible whilst still being meaningful, Figure 6.
  2. Always use standard abbreviations, this will help everyone involved in the project from the project team to the stakeholders to understand the project scope.
  3. Keep the scope description narrow to allow for accurate reporting. If the description is too broad it will be hard to determine an accurate % of completion when work on the project begins.

Summary

Before compiling a list of activities that will describe a deliverable make sure you fully understand the work required to complete the deliverable. Use all the resources available to you including interviewing the experts who are going to do the work and reviewing similar successful projects to ensure you construct a realistic schedule.

Make sure you have a planned start date (a Start Milestone) and a planned finish date (a Finish Milestone) for each group of activities that complete a deliverable. Use the Best Practice Guidelines for naming your activities so that everyone involved in the project understands the project scope. Remember to keep the scope description narrow so that an accurate % of scope can be reported during the project.

We’ve produced a short video, on ‘Best practices for Activities in Primavera P6’.

You can also see other Oracle Primavera P6 videos by Ten Six here as well as subscribe to our YouTube channel to receive notifications of when we post a new video.

For more Primavera P6 articles click here

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management

Archives

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals

Primavera P6 EPPM Fundamentals

Primavera P6 EPPM Administrator

Oracle Primavera P6 BI Publisher Fundamentals Training Class

EVMS Training

Deltek Cobra Fundamentals Training

Deltek Cobra Advanced Training Class

Deltek Acumen Fuse Training Class

Copyright © 2021 · Ten Six Consulting, LLC · 703.910.2600

  • Training
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    ▼
    • Project Management
      ▼
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      ▼
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      ▼
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      ▼
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      ▼
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    ▼
    • Primavera P6
      ▼
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us