Ten Six Consulting

Enterprise project management and earned value management

703-910-2600
  • About Ten Six
  • Consulting Services
    • Project Management Services
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO) Services
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management Services
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs
      • EVMS Staff Augmentation
    • Risk Management Services
      • Risk Management Support and Consulting Services
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management Services
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
  • Software Services
    • Primavera Implementation Consulting
      • Primavera P6 Application Consulting
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 BI Publisher Services
      • Primavera P6 Staff Augmentation
    • Deltek Cobra Implementation Consulting
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
      • Deltek GCS and Cognos Impromptu Services
    • Adrega PI (Project Intelligence)
      • Adrega PI Dashboard Reports
    • Microsoft Project Implementation Services
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Training
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us

Microsoft Project Calendar Detailed Work Hours

You are here: Home / Microsoft Project / Microsoft Project Calendar Detailed Work Hours

December 28, 2016 By Ten Six

If your project start date timestamp does not fall in line with the regularly scheduled work day, then your task finish times may not make sense. Let’s explore this further.

The ‘Change Working Time’ dialogue provides the opportunity to specify detailed workday start and finish times. However, if your project start date and status date timestamps do not match your workweek details then your task finish date time stamp will be off. The same is true for constraint time stamps that do not match the details of the workweek.

This article demonstrates the problem arising from mismatched project start and workweek daily timestamps.

Our demonstration Microsoft Project schedule is displayed in Figure 1.

microsoft-project-calendar-detailed-work-hours-fig-1Figure 1

Note that activities start at 8:00AM and complete at 6:00PM daily. Select the Project tab and Change Working Time, Figure 2.

microsoft-project-calendar-detailed-work-hours-fig-2Figure 2

Select the Work Week tab in the Change Working Time dialog, again, Figure 2. Then select Details, Figure 3.

microsoft-project-calendar-detailed-work-hours-fig-3Figure 3

Note the start and finish times for the 4-day workweek, Figure 4.

microsoft-project-calendar-detailed-work-hours-fig-4Figure 4

The workday begins at 8:00AM and completes at 6:00PM.

Now select the Project tab and Project Information icon, Figure 5.

microsoft-project-calendar-detailed-work-hours-fig-5Figure 5

Set the start date and status date timestamps to 9:00AM, again, Figure 5. Now in Figure 6 we observe the impact these new timestamps have on our schedule.

microsoft-project-calendar-detailed-work-hours-fig-6Figure 6

Observe that our task finish time is now 9:00AM in the morning, which does not make sense. Also, note that our install fence activity has 4.9-days total slack, which also is not what we want. Note that the install fence activity has a Finish No Later Than constraint at 6:00PM, Figure 7.

microsoft-project-calendar-detailed-work-hours-fig-7Figure 7

This is mismatched from our 9:00AM start time. To rectify this situation we set the working times for the workweek to 9:00AM to 7:00PM, Figure 8.

microsoft-project-calendar-detailed-work-hours-fig-8Figure 8

The Finish No Later Than constraint is set to 7:00PM. With these changes our schedule tasks now start at 9:00AM and complete at 7:00PM, Figure 9.

microsoft-project-calendar-detailed-work-hours-fig-9Figure 9

And the install fence activity now has 5-days total slack, which is in line with our workweek schedule.

Summary

If your project start timestamp and detailed workdays do not match than your task start and finish times will be off. Set the project start and any constraint timestamps to match the schedule’s detailed workday. This way your task start and finish timestamps will line up with detailed workday.

Primary Sidebar

  • Facebook
  • Google+
  • Linkedin
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management

Archives

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals

Primavera P6 EPPM Fundamentals

Primavera P6 EPPM Administrator

EVMS Training

Deltek Cobra Fundamentals

Deltek Cobra Advanced

Deltek Acumen Risk Analysis Training

Deltek Acumen Fuse | Risk | 360 Training

BI Publisher for Primavera P6

Copyright © 2018 · Ten Six Consulting, LLC · 703.910.2600

  • About Ten Six
  • Consulting Services
    ▼
    • Project Management Services
      ▼
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO) Services
      ▼
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management Services
      ▼
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs
      • EVMS Staff Augmentation
    • Risk Management Services
      ▼
      • Risk Management Support and Consulting Services
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management Services
      ▼
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
  • Software Services
    ▼
    • Primavera Implementation Consulting
      ▼
      • Primavera P6 Application Consulting
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 BI Publisher Services
      • Primavera P6 Staff Augmentation
    • Deltek Cobra Implementation Consulting
      ▼
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
      • Deltek GCS and Cognos Impromptu Services
    • Adrega PI (Project Intelligence)
      ▼
      • Adrega PI Dashboard Reports
    • Microsoft Project Implementation Services
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Training
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • Contact Us