• Skip to main content
  • Skip to primary sidebar
  • Skip to footer

Ten Six Consulting

Project and Earned Value Management, Primavera P6 & Deltek Cobra & Acumen Services

703-910-2600
  • Training
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    • Project Management
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    • Primavera P6
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us

Setting up a Baseline in Microsoft Project 2013

You are here: Home / Microsoft Project / Setting up a Baseline in Microsoft Project 2013

February 6, 2015 By Ten Six

If you are not sure how to set up a baseline to measure project progress in Microsoft 2013 then you may find this article very helpful.

After completion of the initial planning phase of the project, where the tasks, durations, task relationships, etc. have been entered and scheduled, it is time to make a baseline of the project.

A baseline is a snapshot of all the planned work before commencement of the work. The baseline should be approved by the project manager, sponsor, and other stakeholders, as appropriate. The baseline allows you to clearly display where the schedule is diverting from the original plan.

This article describes how to create a baseline and set up both your task view and Gantt chart view in preparation for measuring project performance in Microsoft Project 2013. Although, the article does provide a few updates it is not intended to provide an exhaustive review of schedule update procedures.

Start and Finish Column Headings

To begin Figure 1 displays a sample schedule with a Gantt chart, tasks, durations, and start and finish dates.

Baseline in Microsoft Project 2013Fig 1
Figure 1

Before we start, it makes sense to change your start and finish columns to estimated start and estimated finish. This is done by right clicking on the respective column heading and selecting Field Setting from the resulting drop down menu, Figure 2.

Baseline in Microsoft Project 2013Fig 2
Figure 2

This brings up your Field Settings dialog. Keep the field name the same, but enter the Title Est Start, Figure 3, for the start column and Est Finish for the finish column.

Baseline in Microsoft Project 2013Fig 3
Figure 3

Setting the Baseline

Next add four columns to your task view: Actual Start, Actual Finish, Baseline Start, and Baseline Finish, Figure 4.

Baseline in Microsoft Project 2013Fig 4
Figure 4

 You will use the Actual Start and Actual Finish columns to enter actual schedule dates, and the Baseline Start and Baseline finish columns will be populated with the baseline dates once a baseline is fixed. Setting the baseline, in fact, is the next step. To set the baseline select the Project tab, Schedule ribbon, Set Baseline drop down menu, and click Set Baseline. This brings up the Set Baseline dialog, Figure 5.

Baseline in Microsoft Project 2013Fig 5
Figure 5

You want to set the baseline for the entire project, as displayed in Figure 5. Once you set the baseline you will notice that Microsoft Project 2013 has populated your Baseline Start and Baseline Finish columns with dates similar to your Estimated Start and Estimated Finish Columns, Figure 6.

Baseline in Microsoft Project 2013Fig 6
Figure 6

Baseline on the Gantt Chart

Now that you have a baseline you want to view it on the Gantt chart. To display the baseline on the Gantt chart select the Task tab, View ribbon, Gantt Chart drop down menu, and click Tracking Gantt. Now you have your baseline displayed in gray and underneath your schedule bars, Figure 7.

Baseline in Microsoft Project 2013Fig 7
Figure 7

You may have noticed that your Gantt chart now displays in days, which makes it too large for ease of viewing. To change the Gantt chart timescale right click on the Gant chart date header and select Timescale, Figure 8.

Baseline in Microsoft Project 2013Fig 8
Figure 8

In the resulting Timescale dialog change the Bottom Tier units from Days to Weeks, Figure 9.

Baseline in Microsoft Project 2013Fig 9
Figure 9

Your schedule will now look similar to Figure 10.

Baseline in Microsoft Project 2013Fig 10
Figure 10

One last thing to change before commencing with project updates. You will want to change the Gantt chart labels to display the total slack. To do this select the Format tab, Bar Styles ribbon, Format drop down menu, and click Bar Styles. The Bar Styles dialog will appear, Figure 11.

Baseline in Microsoft Project 2013Fig 11
Figure 11

As shown in Figure 11, change the Text for Critical, Task, and Summary (not in figure) to Total Slack. Now your schedule with baseline is ready for updates, Figure 12.

Baseline in Microsoft Project 2013Fig 12
Figure 12

Updates

To begin updating the schedule select the Project Start milestone and then select the Task tab, Schedule ribbon, and 100% icon, Figure 13. Microsoft Project 2013 will automatically populate the Actual Start and Actual Finish columns, again, Figure 13.

Baseline in Microsoft Project 2013Fig 13
Figure 13

Now highlight the Mobilize task and in the Actual Start column enter Wed 1/7/15, Figure 14, which shows that the task stated on time.

Baseline in Microsoft Project 2013Fig 14
Figure 14

However, in the Actual Finish column enter a finish date of 1/26/15, which shows that the task completed one business day late, Figure 14. When you enter the late finish date the warning message in Figure 15 will appear.

Baseline in Microsoft Project 2013Fig 15
Figure 15

Select OK to say you understand the resource assignment is outside the original dates for Task 3 Mobilize. After entering the late finishing Mobilize task the Gantt chart will look similar to Figure 16.

Baseline in Microsoft Project 2013Fig 16
Figure 16

Because the Mobilize task is on the critical path all the tasks succeeding Mobilize will be one day delayed. Now let’s say you update your task up to and including the 1st of February, 2015. Again use the Task tab, Schedule ribbon, and % icons to define progress. As described in Figure 17, update the Grade Site task by saying it is 50% complete and the Set Foundation task by saying it is 75% complete.

Baseline in Microsoft Project 2013Fig 17
Figure 17

You now have your schedule, including a baseline, and a few updates to send you on your way toward measuring project progress, and analyzing the relative success of your project.

Summary

In addition to setting the baseline, you will need to add actual and baseline columns to your task view, and also use the Tracking Gantt chart to view the baseline in the Gantt chart. Once the baseline is set and your task view and Gantt chart view adjusted for easy progress measurement, you are ready to commence updates.

It is highly recommended that you create a copy of your schedule and baseline before proceeding with the update procedures. Microsoft Project 2013 provides several ways to update your project progress, which you can explore in more detail having prepared your schedule for updates.

After completion of the initial planning phase of the project, where the activities, activity durations, and activity relationships have been successfully entered and scheduled, it is time to make a baseline of the project. The baseline is a complete copy of the project that is linked to the original project. The baseline allows you to clearly display where the project is diverting from the original plan.

Primary Sidebar

  • This field is for validation purposes and should be left unchanged.
  • Facebook
  • LinkedIn
  • Twitter

Categories

  • Deltek Acumen
  • Deltek Cobra
  • Earned Value Mgmt
  • Microsoft Project
  • PMO
  • Primavera P6
  • Project Management
  • Risk Management

Archives

Footer

Upcoming Classes

Primavera P6 Professional Fundamentals

Primavera P6 EPPM Fundamentals

Primavera P6 EPPM Administrator

Oracle Primavera P6 BI Publisher Fundamentals Training Class

EVMS Training

Deltek Cobra Fundamentals Training

Deltek Cobra Advanced Training Class

Deltek Acumen Fuse Training Class

Copyright © 2021 · Ten Six Consulting, LLC · 703.910.2600

  • Training
    ▼
    • Primavera P6 Training
    • Deltek Training
    • Microsoft Project Training
    • Project Management Training
    • Earned Value Management Training
    • Open Training Class Dates
    • Customized Video Training Classes
  • Consulting
    ▼
    • Project Management
      ▼
      • Assessments and Health Checks
      • Organizational Change Management
      • Project Governance
      • Project Management Tool Selection
      • Risk Analysis Services
      • Scheduling Services
      • Project Management Staff Augmentation
    • Project Management Office (PMO)
      ▼
      • PMO Pulse Check
      • PMO Implementation Planning
      • PMO Organization Change Management
      • PMO Project Manager Leadership Development
      • PMO Planning Best Practices
      • PMO Scheduling Best Practices
      • PMO Enterprise Tool Training
      • Program Manager Challenges
    • Earned Value Management
      ▼
      • EVMS RFP Support
      • EVMS Assessments
      • Earned Value Management Tool Selection
      • EVMS System Description and Process Development
      • Integrated Baseline Review (IBR) Preparation and Conduct
      • EVM Certification Support
      • Integrated Master Schedule (IMS) Health Check
      • Action Plan Development for Progress Assessment Reviews
      • Earned Value Data Analysis and Reporting
      • WBS Guidelines for Government Acquisition Programs (MIL-STD 881D)
      • EVMS Staff Augmentation
    • Risk Management
      ▼
      • Risk Management Support and Consulting
      • Risk Management Maturity Assessment® (RMMA)
      • Risk Management Checkup Services (RMCS®)
      • Risk Management Training and Workshops
    • Portfolio Management
      ▼
      • IT Portfolio Management
      • Corporate Governance Portfolio Management
      • Product Portfolio Management
      • Public Sector Portfolio Management
      • New Product Development Portfolio Management
    • ISO 21500 Assessment
  • Software
    ▼
    • Primavera P6
      ▼
      • Primavera P6 Application Consulting
      • Primavera P6 BI Publisher Services
      • Primavera P6 Technical Consulting
      • Primavera P6 Integration
      • Primavera P6 Knowledge Transfer, Mentoring and Coaching
      • Primavera P6 Staff Augmentation
    • Primavera Unifier
    • Deltek Cobra
      ▼
      • Deltek Cobra Application Consulting
      • Deltek Cobra Knowledge Transfer, Coaching and Mentoring
      • Deltek Cobra Integration
      • Deltek Cobra Staff Augmentation
    • Microsoft Project
      ▼
      • Building an Integrated Master Schedule (IMS)
      • Integrating Microsoft Project with Deltek Cobra
      • Migrating From Microsoft Project To Oracle Primavera P6
      • Microsoft Project to Primavera P6 Conversion Service
  • Blog
    ▼
    • Deltek Acumen
    • Deltek Cobra
    • Earned Value Mgmt
    • Microsoft Project
    • PMO
    • Primavera P6
    • Project Management
    • Risk Management
  • Clients
  • About Ten Six
  • Contact Us