Deltek Cobra Integration Warning
[Warning]Invalid budget class ‘Budget’ for ‘2.3.3’, ID ‘3.3.3’
Explanation:
Do you get this error message [Warning]Invalid budget class ‘Budget’ for ‘2.3.3’, ID ‘3.3.3’? This rather obscure warning is typically found in the Deltek Cobra integration log when a resource has been assigned incorrectly to a Control Account that has no Work Package definition in the Microsoft Project schedule. In other words, it has likely been assigned to a summary task that has a control account defined, but has no work package defined at the same level.
The reason Deltek Cobra is stating that it is an invalid budget class is because, in this instance, the budget class has been defined at the work package level in the Project Information > Classes tab.
The schedule, however, is attempting to load the resource as the Control Account level, where no such class exists – hence the strange warning.
Solution:
Reassign the resource to a work package task below the control account summary row in the Microsoft Project schedule.